I. Background  

Company N (“Company N” or “Ordering Company”), which has built and operates power generation plant Y (“Plant Y”), provided the design and engineering materials (“Design and Engineering Materials”) it received from Company A, an engineering company (“Company A” or “Design Engineering Company”) that designed power generator units 3 and 4 of the power generation plant Y, to Company B so that the company could refer to them when designing the power generator units 5 and 6 for Plant Y.  No explicit contract concerning the owners and right of use of the Design and Engineering Materials exists between Company N and Company A.